Please see below for updates on our current Facility and Parks improvement projects.  The most recent updates will be listed at the top of the page in descending order.   

Renovation of the pool area at Club Fitness

October 28, 2024: the whirlpool re-opened.  

October 22, 2024: the pool re-opened.  

October 19, 2024: the pool has been filled and chemicals are being checked.  The plan is to re-open the pool on Tuesday, October 22, 2024.

October 18, 2024: the whirlpool is being plastered and the process of filling the pool has begun.

October 16, 2024: the pool floor is being polished.

October 11, 2024: new flooring is being installed in the pool area.

October 7, 2024: the heating panels have been hung, reconnected and painted.  The floor is being prepped for the installation of new flooring.  

September 19, 2024: the floor in the pool area is being grounded down to cement in preparation for the installment of new flooring.  

September 17, 2024: work continues on the rooftop above the “build-outs” on the west facing wall of the pool area.  The painting of the walls has been completed.  Today through Thursday, the heating panels will be lifted, installed and pipes will be reconnected.  

September 11, 2024: the walls are being painted.  

September 9, 2024: the walls are being primed to be painted.  

September 3, 2024: the surface of the whirlpool is being repaired and new grout and tile are being installed.   

Centennial Recreation Center New Roof Installation  

Wednesday, August 28, 2024: Work continues on the 3 “Build Outs,” the walls on the west side of the pool area, nearing completion.  Demolition continues on the whirlpool.  

Thursday, August 15, 2024: During the installation of the new roof, it was discovered that the area of the roof in the pool area that connects to the exterior wall is failing; therefore, additional planning and resource approval was needed.  Sprinkler, steel, roofing, masonry and dry wall repairs will begin.  We project this phase will take approximately 4 weeks once construction begins.  We apologize for this inconvenience; the construction issues were not previously known until the roofers opened up the area during the roof replacement process.

Friday, July 19, 2024: ALL of Club Fitness and Centennial Gymnasium with the basketball court will be shut down through Sunday, July 21, 2024. We will reopen Monday, July 22, 2024.

July 15, 2024: weather permitting, the roofers will begin working on the roof over the Centennial Gymnasium (with the basketball court) the following days, which will affect some pickleball and open gym basketball programming:

• Friday, July 12, 2024
• Saturday, July 13, 2024
• Monday, July 15, 2024
• Tuesday, July 16, 2024
 
The basketball courts will NOT need to be shut down the entire day, just during the roof removal process. Therefore, for each of the days listed above, the gym (with the basketball court) will need to be shut down from 5:00 a.m. to 10:00 a.m. Thank you for your patience during this time.
 
Saturday’s Basketball Open Gym will run from 10 a.m. – 11:30 a.m., and Tuesday’s Pickleball Open Gym will run between 10:30 a.m. and 12:30 p.m.
 

July 11, 2024: Club Fitness: on the Fitness Floor at Club Fitness, about half of the equipment is closed (we will make an announcement on the Club Fitness facebook page once this area re-opens.) The outside lane of the track is open for walkers.

 
July 8, 2024

Only half of the basketball gym remains open as work continues on the roof on the other half of the gym.  

July 3, 2024

A portion of the fitness floor walking track at Club Fitness and some of the equipment (squat racks and Smith machine) have been closed as work resumes on the roofing project. As soon as these areas re-open, we will post it here and on the facebook Club Fitness page.  The area has been re-opened.  

June 20, 2024

Centennial Gym (with the Basketball Court) will be closed until July 1, as work on the roof above the gym is being conducted.  When the gym re-opens on July 1, only have of the gym will be open.      

May 31, 2024

To the Community of Addison,

The Addison Park District is excited to announce our $1.5 million facility improvement project for Centennial Recreation Center, 1776 W. Centennial Place, will begin on Tuesday, June 4, 2024. Centennial Recreation Center is home to Club Fitness, our indoor pool, Centennial Gym, NEDSRA, and Athletico.
The project’s scope of work includes a new roof, water damage repairs, and preparations to install the park district’s first ever air conditioning unit at Centennial Gym, making the gym comfortable and accessible during the summer months, which will greatly benefit the community. This project is expected to take approximately 2 months and involves: demolition of the existing roof, installation of a new roof, repair of water damage, painting, sealing, prepping for the air conditioning unit, electrical and plumbing work, etc.
Staff had a kick-off meeting with the contractor this morning, Friday, May 31, and we learned the contractor is requiring us to close portions of the facility during this renovation project for the safety of our staff and patrons.
The first closure will be the pool, which will begin on Tuesday, June 4th, and we anticipate it will be closed for 2 months, while the contractor fixes and repairs the internal water damage in the pool area. If we are able to open it earlier, we will make an announcement. With the closure of the pool, there will be no group aquatic classes, swim lessons, or open swim during this time. We sincerely apologize, as it is never our desire to cancel programs or close facilities. We are currently researching other opportunities to run these programs during the closure.
As we receive updated closure information from the contractor, we will announce these temporary closures and updates in the following ways:

* On the website at addisonparks.org/projects
* Social Media on the Club Fitness Facebook page
* Signage inside the building

Lastly, please be patient with this process. Our staff is here to help answer questions but may not have all of the answers since we are in the beginning stages of this project.